Looking at stage 8 of the procurement and supply cycle, what does TCA mean?

Suggested Answer:

See the answer in explanation.
Explanation:
When evaluating offers, it is important to remember that the best price may not be the lowest. To ascertain that; the total cost of Acquisition TCA (the cost a buyer bears for placing orders and re-ceiving a product from a supplier) should be uncovered and compare against offers received. Things to consider that might make up the total cost of acquisition are;
1) logistics and handling costs
2) Cost of requisition
3) Rework
4) stock cost
5) Delay
6) Inspection
7) customer services
8) consumables
9) Training & support

by Ursula at Aug 08, 2026, 03:07 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10