Exam C-TS412-2021 Topic 4 Question 60 Discussion
Actual exam question for SAP's C-TS412-2021 exam
Question #: 60
Topic #: 4
Question #: 60
Topic #: 4
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use ?
Suggested Answer: A Vote an answer
To extrapolate the basic dates of subordinate WBS elements without taking into account the basic dates of higher-level WBS elements, you can use free planning as the planning method for basic dates. Free planning is a type of planning method for basic dates that allows you to plan dates for WBS elements without any restrictions or dependencies on other WBS elements. Free planning does not consider any hierarchical relationships between WBS elements when calculating their dates. Free planning gives you maximum flexibility and control over your date planning for WBS elements. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
by Guy at Dec 19, 2025, 11:44 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).