What criteria does the Scrum team use to sequence the product backlog? Note: There are 2 correct answers to this question.

Suggested Answer: B,D Vote an answer

The Scrum team prioritizes the backlog based on business priority, ensuring that high-value items are addressed first. Technical dependencies are also considered to prevent delays and ensure smooth workflow across sprints.