Exam C_S4PM_2504 Topic 2 Question 71 Discussion
Actual exam question for SAP's C_S4PM_2504 exam
Question #: 71
Topic #: 2
Question #: 71
Topic #: 2
Which type of testing should be done after a release upgrade has occurred?
Suggested Answer: A Vote an answer
Release upgrades in SAP S/4HANA Cloud Public Edition introduce new features and updates, necessitating testing to ensure system stability.
* Option A: Regression testsCorrect. Regression testing is performed after a release upgrade to verify that existing functionalities continue to work as expected. SAP's official documentation recommends regression testing to validate that new changes do not negatively impact core processes.
* Option B: User Acceptance testsIncorrect. User Acceptance Testing (UAT) is typically conducted during the initial implementation or major configuration changes, not specifically after a release upgrade.
* Option C: String testsIncorrect. String tests validate specific process flows during implementation, not post-upgrade scenarios.
* Option D: Integration testsIncorrect. Integration tests focus on system connectivity during implementation, not post-upgrade validation of existing functionality.
:
SAP S/4HANA Cloud Testing Guide: Recommends regression testing post-upgrade (https://help.sap.com).
SAP Activate Methodology: Includes regression testing in the Deploy phase for upgrades.
SAP S/4HANA Cloud Public Edition Study Guide: Highlights testing strategies for release upgrades.
* Option A: Regression testsCorrect. Regression testing is performed after a release upgrade to verify that existing functionalities continue to work as expected. SAP's official documentation recommends regression testing to validate that new changes do not negatively impact core processes.
* Option B: User Acceptance testsIncorrect. User Acceptance Testing (UAT) is typically conducted during the initial implementation or major configuration changes, not specifically after a release upgrade.
* Option C: String testsIncorrect. String tests validate specific process flows during implementation, not post-upgrade scenarios.
* Option D: Integration testsIncorrect. Integration tests focus on system connectivity during implementation, not post-upgrade validation of existing functionality.
:
SAP S/4HANA Cloud Testing Guide: Recommends regression testing post-upgrade (https://help.sap.com).
SAP Activate Methodology: Includes regression testing in the Deploy phase for upgrades.
SAP S/4HANA Cloud Public Edition Study Guide: Highlights testing strategies for release upgrades.
by Kenneth at Dec 16, 2025, 06:47 AM