Exam C_TS412_2021 Topic 4 Question 91 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 91
Topic #: 4
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?

Suggested Answer: D Vote an answer

To determine the requirement date for a material component assigned to a network activity, you have to maintain the basic dates of the network activity. The basic dates are the earliest possible start and finish dates of an activity or a network, based on its dependencies and constraints. The requirement date for a material component is derived from the basic start date of the activity to which it is assigned. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html

by Tiffany at Oct 11, 2025, 03:48 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10