Question #: 13
Topic #: 3
What information do you have to maintain to define the relationship between supply source and demand source in the Kanban process? Note: There are 2 correct answers to this question.

Suggested Answer: C,D Vote an answer

In SAP S/4HANA, the Kanban process links supply and demand sources via thecontrol cycle(transaction PKMC). Required information includes:
* Replenishment strategy(C): In the control cycle (PKMC, field: Replenishment Strategy), you define how replenishment occurs (e.g., "0001" for in-house production, "0003" for external procurement,
"0002" for stock transfer). This strategy specifies the supply source (e.g., production, vendor) and how it meets demand at the Kanban bin.
* Production supply area(D): The PSA (defined in Customizing, transaction PK05, and assigned in PKMC) represents the demand source-where the material is consumed (e.g., a specific production line). It connects the Kanban bin to the supply source (e.g., storage location or work center).
Routing(A) (CA21) details operations for production but isn't directly maintained in the control cycle-it's referenced via the production version.Work Center(B) (CR02) is linked indirectly via the PSA or production version, not a direct control cycle field. This is per SAP's Kanban configuration.

by Sam at Oct 09, 2025, 07:27 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10