Exam C_TS422_2023 Topic 3 Question 34 Discussion

Actual exam question for SAP's C_TS422_2023 exam
Question #: 34
Topic #: 3
What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?

Suggested Answer: C Vote an answer

When you assign a planned order to a production line manually, using the planning table in repetitive manufacturing, the system generates capacity requirements for the planned order. The capacity requirements are calculated based on the production line, the quantity, and the production rate of the planned order. The system also checks the availability of the production line and displays any capacity overload or underload. The planned order is not converted to a production order, nor is the component availability or the picking list affected by the manual assignment. Reference: SAP Help Portal - Assigning Planned Orders to Production Lines, SAP S/4HANA Production Planning and Manufacturing Certification Guide - Chapter 7: Repetitive Manufacturing

by Yves at Feb 05, 2025, 08:19 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10