When do you perform Quality Gate (Q-Gate) during a project? Note: There are 2 correct ans-wers to this que-stion.
Suggested Answer: A,B Vote an answer
Quality Gates (Q-Gates) are performed during a project at specific phases to ensure quality and readiness for the next phase:
* A. At the end of Realize phase: This is a critical checkpoint to assess if the project deliverables are ready for deployment and meet the set expectations.
* B. At the end of Prepare phase: Marks the completion of initial project setup and planning, ensuring all elements are in place for the project's execution phase. Options C (At the end of Discover phase) and D (At the end of Run phase) are not typically associated with Quality Gates in the SAP Activate methodology.References:
* SAP Activate project planning and control
* Implementation standards within SAP projects
* A. At the end of Realize phase: This is a critical checkpoint to assess if the project deliverables are ready for deployment and meet the set expectations.
* B. At the end of Prepare phase: Marks the completion of initial project setup and planning, ensuring all elements are in place for the project's execution phase. Options C (At the end of Discover phase) and D (At the end of Run phase) are not typically associated with Quality Gates in the SAP Activate methodology.References:
* SAP Activate project planning and control
* Implementation standards within SAP projects
by Kent at Oct 29, 2025, 06:52 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).