Exam E_ACTAI_2403 Topic 4 Question 31 Discussion

Actual exam question for SAP's E_ACTAI_2403 exam
Question #: 31
Topic #: 4
When do you perform Quality Gate (Q-Gate) during a project? Note: There are 2 correct ans-wers to this que-stion.

Suggested Answer: A,B Vote an answer

Quality Gates (Q-Gates) are performed during a project at specific phases to ensure quality and readiness for the next phase:
* A. At the end of Realize phase: This is a critical checkpoint to assess if the project deliverables are ready for deployment and meet the set expectations.
* B. At the end of Prepare phase: Marks the completion of initial project setup and planning, ensuring all elements are in place for the project's execution phase. Options C (At the end of Discover phase) and D (At the end of Run phase) are not typically associated with Quality Gates in the SAP Activate methodology.References:
* SAP Activate project planning and control
* Implementation standards within SAP projects

by Leonard at Jan 16, 2025, 11:51 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10