Exam E_ACTAI_2403 Topic 6 Question 35 Discussion
Actual exam question for SAP's E_ACTAI_2403 exam
Question #: 35
Topic #: 6
Question #: 35
Topic #: 6
What is the basis for approving work results (signing Act of Acceptance) on Project Phase level?
Suggested Answer: C Vote an answer
The basis for approving work results (signing Act of Acceptance) on Project Phase level in the context of SAP Activate involves:
* C. Agreed and met Acceptance Criteria within quality gate: This entails having predefined and mutually agreed-upon criteria that must be met to ensure the deliverables meet the required standards and expectations before moving to the next phase. Options A (Steering committee meeting decision), B
* (Definition of Done for User Story), and D (Definition of Done for Sprint) are relevant in broader project management and Agile contexts but specifically for SAP Activate, the acceptance criteria defined within quality gates are critical for approval.References:
* SAP Activate methodology guidelines
* Quality management in SAP projects
* C. Agreed and met Acceptance Criteria within quality gate: This entails having predefined and mutually agreed-upon criteria that must be met to ensure the deliverables meet the required standards and expectations before moving to the next phase. Options A (Steering committee meeting decision), B
* (Definition of Done for User Story), and D (Definition of Done for Sprint) are relevant in broader project management and Agile contexts but specifically for SAP Activate, the acceptance criteria defined within quality gates are critical for approval.References:
* SAP Activate methodology guidelines
* Quality management in SAP projects
by Belinda at Nov 26, 2025, 06:56 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).