There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?
Correct Answer: B Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
When a fragnet of activities represents a known schedule risk, which activity will most likely change the overall outcome?
Correct Answer: A Vote an answer
When should the Project Plan have incorporated the relevant interfaces and requirements of the project contract documents?
Correct Answer: C Vote an answer
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?
Correct Answer: A Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
Correct Answer: D Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that
Correct Answer: A Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
How much Total Float does drafting the product manual have?
Correct Answer: A Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.
The contractor subsequently submits a CPM schedule for its baseline schedule submittal. As part of your review, you look at the durations for each activity in the schedule. How do you determine if a duration of 10 work days for drywall installation is accurate?
Correct Answer: C Vote an answer
Resource planning must take all of the following into account except for:
Correct Answer: B Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).