During a Sprint, the team completes four stories with story points 3, 5, 8 and 2 respectively. They further complete half a story with a story point of 13.
What is the velocity of the team?
Correct Answer: A Vote an answer
What is an information radiator?
Correct Answer: C Vote an answer
Who is responsible for implementing the actions agreed upon by the team during a Retrospective?
Correct Answer: B Vote an answer
Who knows most about the progress towards a business objective or a release?
Correct Answer: C Vote an answer
Agile planning happens at multiple levels including a daily plan, an sprint plan and a strategic plan.
What term best describes the multi-level planning?
Correct Answer: A Vote an answer
A team is estimating story points. They estimate that the story falls between a large (13) and a medium (5) and they assign a story point of 8.
What is this technique called?
Correct Answer: B Vote an answer