Exhibit:

The client has a strong skill base/interest in a Linux RHEL-based virtualized solution. One of their key requirements is to be able to quickly provision new compute nodes. Which PureFlex systems management capability should be highlighted to them?
Correct Answer: C Vote an answer
A client has purchased a Flex System with a Flex System Manager (FSM) and a p260 node. Which of the following is the most cost-effective procedure to install the VIO server?
Correct Answer: D Vote an answer
A hardware error is automatically reported to IBM. An IBM Flex System Fabric EN4093R switch with upgrade 2 needs to be replaced. The technician is going to the client with the new switch and replaces the switch. What additional step must be taken for the new switch to be operational?
Correct Answer: D Vote an answer
A sales team needed to complete a PureFlex proposal before they had the opportunity to sort out the details of networking connectivity with the client networking team. Therefore, they did not change the networking defaults from the configuration. What consequences might result from this approach?
Correct Answer: C Vote an answer
A cost conscious client wants to purchase a two POWER node PureFlex solution. Each node will have 16 cores, two AIX LPARs, and they need four ports of FCoE communications. A critical requirement is there can be no single point of failure. Which solution will meet all the client's requirements?
Correct Answer: D Vote an answer
A large enterprise client wants to perform a benchmark on a PureFlex System to compare the performance against a competitive solution. What is the best way for the client to proceed?
Correct Answer: D Vote an answer
A client has a need for a Linux based solution that requires a large amount of memory. The application runs on either x86 or Power nodes. Which of the following nodes would provide the maximum memory configuration?
Correct Answer: A Vote an answer