Which of the following is a defect that is more likely to be found by a static analysis tool than by other testing techniques?
Correct Answer: D Vote an answer
Which of the following are the typical defects found by static analysis tools?
a. Variables that are never used.
b. Security vulnerabilities.
c. Poor performance.
d. Unreachable code.
e. Business processes not followed.
Correct Answer: C Vote an answer
What if the project isn't big enough to justify extensive testing..?
Correct Answer: A Vote an answer
Which of the following is least likely to be used as a technique to identify project and product risks? 1 credit
Correct Answer: A Vote an answer
The test improvement project will take place in an organization developing a safety-critical avionics application. Which one of the following standards do you believe would be most appropriate to take into account for compliance during your assignment? 1 credit
Correct Answer: B Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
Which of the following test case design techniques is white box (structure-based)? [K1]
Correct Answer: D Vote an answer
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test
b. strategy document
c. The overall estimated costs, timescales and resource
d. requirements
e. A detailed schedule of testing activities
f. The development deliverables to be tested
g. Which test staff members (names) will be involved and when
h. Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit
Correct Answer: C,D Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
Which of the main activities of the fundamental test process does the task 'verify the test environment set up is correct' relate to? [K1]
Correct Answer: C Vote an answer
A garden irrigation system allows the user to specify 2 inputs:
1. Frequency - The number of times the system should be automatically switched on per day; minimum once per day, maximum 5 times
2. Duration - The duration of operation, in whole minutes, each time it is switched on; ranging from 1 to 60
Applying 2-value boundary value analysis which of the following options has the correct test set of valid and invalid boundary values?
Correct Answer: A Vote an answer
Part of the testing strategy indicates that you are going to be using systematic test design techniques. Your manager has asked that you present the main advantages of using these techniques at the next board meeting. Identify THREE main benefits of using systematic test design techniques within this company. 2 credits (for 2 out of 3 correct 1 credit)
Correct Answer: A,B,G Vote an answer