You are designing a data warehouse that uses SQL Server 2012.
The data warehouse contains a table named factSales that stores product sales. The table has a clustered index on the primary key, four foreign keys to dimension tables, and an aggregate column for sales totals. All key columns use the INT data type, and the aggregate column uses the MONEY data type.
You need to increase the speed of data retrieval from the factSales table.
Which index type should you add to the table?
The data warehouse contains a table named factSales that stores product sales. The table has a clustered index on the primary key, four foreign keys to dimension tables, and an aggregate column for sales totals. All key columns use the INT data type, and the aggregate column uses the MONEY data type.
You need to increase the speed of data retrieval from the factSales table.
Which index type should you add to the table?
Correct Answer: B
Vote an answer
You are designing a SQL Server Integration Services (SSIS) project that uses the Project Deployment Model.
The project will contain 10 packages. All the packages must connect to the same data source and destination.
You need to define and reuse the connection managers in all the packages by using the least development effort.
What should you do?
The project will contain 10 packages. All the packages must connect to the same data source and destination.
You need to define and reuse the connection managers in all the packages by using the least development effort.
What should you do?
Correct Answer: A
Vote an answer
You are a data warehouse developer responsible for developing data cleansing processes.
Duplicate employees exist in an employee dimension.
You need to map, discover, and manage domain values based on the employee dimension.
Which Data Quality Services (DQS) option should you use? (To answer, select the appropriate option in the answer area.)

Duplicate employees exist in an employee dimension.
You need to map, discover, and manage domain values based on the employee dimension.
Which Data Quality Services (DQS) option should you use? (To answer, select the appropriate option in the answer area.)

Correct Answer:

Explanation

You are implementing a SQL Server Integration Services (SSIS) package that imports Microsoft Excel workbook data into a Windows Azure SQL Database database. The package has been deployed to a production server that runs Windows Server 2008 R2 and SQL Server 2012.
The package fails when executed on the production server.
You need to ensure that the package can load the Excel workbook data without errors. You need to use the least amount of administrative effort to achieve this goal.
What should you do?
The package fails when executed on the production server.
You need to ensure that the package can load the Excel workbook data without errors. You need to use the least amount of administrative effort to achieve this goal.
What should you do?
Correct Answer: C
Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
You are developing a SQL Server Integration Services (SSIS) project to read and write data from a Windows Azure SQL Database database to a server that runs SQL Server 2012.
The connection will be used by data flow tasks in multiple SSIS packages. The address of the target Windows Azure SQL Database database will be provided by a project parameter.
You need to create a solution to meet the requirements by using the least amount of administrative effort and maximizing data flow performance.
What should you do?
The connection will be used by data flow tasks in multiple SSIS packages. The address of the target Windows Azure SQL Database database will be provided by a project parameter.
You need to create a solution to meet the requirements by using the least amount of administrative effort and maximizing data flow performance.
What should you do?
Correct Answer: C
Vote an answer
You have a SQL Server data warehouse that contains all of the customer data for your company.
You plan to deploy an archiving solution.
You need to move a table named OLDCUSTOMERS to a new storage device. OLDCUSTOMERS contains a clustered index.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
NOTE: More than one order of answer choices is correct. You will receive credit for any of the correct orders you select.

You plan to deploy an archiving solution.
You need to move a table named OLDCUSTOMERS to a new storage device. OLDCUSTOMERS contains a clustered index.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
NOTE: More than one order of answer choices is correct. You will receive credit for any of the correct orders you select.

Correct Answer:

Explanation

You are developing a SQL Server Integration Services (SSIS) package that loads data into a data warehouse hosted on Windows Azure SQL Database.
You must combine two data sources together by using the ProductID column to provide complete details for each record. The data retrieved from each data source is sorted in ascending order by the ProductID column.
You need to develop a data flow that imports the data while meeting the requirements.
How should you develop the data flow? (To answer, drag the appropriate transformation from the list of transformations to the correct location in the answer area.)

You must combine two data sources together by using the ProductID column to provide complete details for each record. The data retrieved from each data source is sorted in ascending order by the ProductID column.
You need to develop a data flow that imports the data while meeting the requirements.
How should you develop the data flow? (To answer, drag the appropriate transformation from the list of transformations to the correct location in the answer area.)

Correct Answer:

Explanation

A Data Flow task in a SQL Server Integration Services (SSIS) package produces run-time errors.
You need to edit the package to log specific error messages.
Which three actions should you perform in sequence? (To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.)

You need to edit the package to log specific error messages.
Which three actions should you perform in sequence? (To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.)

Correct Answer:

Explanation

You develop a SQL Server Integration Services (SSIS) project by using the Package Deployment Model. A package in the project extracts data from a Windows Azure SQL Database database.
The package is deployed to SQL Server.
The package is not producing the desired results.
You need to generate the .mdmp and .tmp debug files in order to troubleshoot the issues.
What should you do?
The package is deployed to SQL Server.
The package is not producing the desired results.
You need to generate the .mdmp and .tmp debug files in order to troubleshoot the issues.
What should you do?
Correct Answer: C
Vote an answer
You are developing a SQL Server Integration Services (SSIS) package.
You need to design a package to change a variable value during package execution by using the least amount of development effort.
What should you use?
You need to design a package to change a variable value during package execution by using the least amount of development effort.
What should you use?
Correct Answer: A
Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
To facilitate the troubleshooting of SQL Server Integration Services (SSIS) packages, a logging methodology is put in place.
The methodology has the following requirements:
*The deployment process must be simplified.
*All the logs must be centralized in SQL Server.
*Log data must be available via reports or T-SQL.
*Log archival must be automated.
You need to configure a logging methodology that meets the requirements while minimizing the amount of deployment and development effort.
What should you do?
The methodology has the following requirements:
*The deployment process must be simplified.
*All the logs must be centralized in SQL Server.
*Log data must be available via reports or T-SQL.
*Log archival must be automated.
You need to configure a logging methodology that meets the requirements while minimizing the amount of deployment and development effort.
What should you do?
Correct Answer: E
Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
You are completing the installation of the Data Quality Server component of SQL Server Data Quality Services (DQS).
You need to complete the post-installation configuration.
What should you do?
You need to complete the post-installation configuration.
What should you do?
Correct Answer: D
Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
You are developing a SQL Server Integration Services (SSIS) package that imports data into a data warehouse.
You are developing the part of the SSIS package that populates the ProjectDates dimension table.
The business key of the ProjectDates table is the ProjectName column. The business user has given you the dimensional attribute behavior for each of the four columns in the ProjectDates table:
*ExpectedStartDate - New values should be tracked over time.
*ActualStartDate - New values should not be accepted.
*ExpectedEndDate - New values should replace existing values.
*ActualEndDate - New values should be tracked over time.
You use the SSIS Slowly Changing Dimension Transformation.
You must configure the Change Type value for each source column.
Which settings should you select? (To answer, select the appropriate setting or settings in the answer area.
Each Change Type may be used once, more than once, or not at all.)

You are developing the part of the SSIS package that populates the ProjectDates dimension table.
The business key of the ProjectDates table is the ProjectName column. The business user has given you the dimensional attribute behavior for each of the four columns in the ProjectDates table:
*ExpectedStartDate - New values should be tracked over time.
*ActualStartDate - New values should not be accepted.
*ExpectedEndDate - New values should replace existing values.
*ActualEndDate - New values should be tracked over time.
You use the SSIS Slowly Changing Dimension Transformation.
You must configure the Change Type value for each source column.
Which settings should you select? (To answer, select the appropriate setting or settings in the answer area.
Each Change Type may be used once, more than once, or not at all.)

Correct Answer:

Explanation

References:
http://msdn.microsoft.com/en-us/library/ms141715.aspx
http://msdn.microsoft.com/en-us/library/ms141662.aspx