Microsoft Managing Projects with Microsoft Project 2013 - 074-343 FREE EXAM DUMPS QUESTIONS & ANSWERS

You are a project manager who uses Project Professional 2013.
Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week.
You need to set up their calendars to reflect the job-sharing arrangement.
What should you do?
Correct Answer: A Vote an answer
You are a project manager for a software development company. You use Project Professional 2013.
You manage an integration project, and you discover that you need to add additional resources to the integration tasks in order to meet your development complete milestone date. The project is behind schedule, so you must shorten the duration of the integration development work.
You identify two additional resources to work on the integration task. When you add these resources, your task now shows it will complete three days ahead of schedule, which leaves a contingency window for issues that may arise.
In order to shorten the duration of the task when the resources are added, you need to set the task type before adding the resources.
What should you do?
Correct Answer: D Vote an answer
You are using Microsoft Project Professional 2013.
Three years ago, you successfully completed a project to review all of the suppliers within your organization, and you have been asked to run a similar project again. You still have the project plan from three years ago.
You need to use the most efficient method to produce a new plan with tasks based upon the old project plan.
What should you do?
Correct Answer: B Vote an answer
You are a project manager who uses Project Professional 2013.
You have created a project which involves three other colleagues who are also using Project Professional 2013. You and your colleagues are over budget and cannot spend any more money on this project.
To ensure that the latest version of the project file is always the one being used, you need to save, share, and sync this project plan File among your colleagues without using email.
What should you do?
Correct Answer: A Vote an answer
You manage a project by using Project Professional 2013.
A critical task is out of scope for the project. The stakeholders suggest that the task be removed from the project but kept in the plan in case the task is needed in the future.
You need to implement a solution to meet the stakeholder's request.
What should you do?
Correct Answer: D Vote an answer
You are a program manager who uses Project Professional 2013.
You manage a portfolio of projects for a large point of sale implementation. All of your project managers have created individual project schedules. You discover that you have resource constraints since multiple resources are working on multiple projects.
You need visibility into resources across all projects so that you can most efficiently manage the resources and their availability.
What should you do?
Correct Answer: B Vote an answer
You are managing a project by using Project Professional 2013, and you notice a potential scheduling problem indicated by wavy red lines under some of the dates in the Finish column.
You need to resolve the issue.
What should you do?
Correct Answer: C Vote an answer