Microsoft Managing Projects with Microsoft Project 2013 - 74-343 FREE EXAM DUMPS QUESTIONS & ANSWERS
Your project managers manage several projects using Project Professional 2013. Each individual project contains a saved baseline.
You need to capture in the master project the baseline data from the member projects at the summary levels for reporting purposes.
What should you do?
You need to capture in the master project the baseline data from the member projects at the summary levels for reporting purposes.
What should you do?
Correct Answer: C
Vote an answer
You are tracking a project schedule by using Microsoft Project. The project schedule contains a baseline.
You need to display a view that displays the slippage of the current plan as compared to the baseline for the schedule.
Which two actions will achieve the goal? Each correct answer presents a complete solution.
You need to display a view that displays the slippage of the current plan as compared to the baseline for the schedule.
Which two actions will achieve the goal? Each correct answer presents a complete solution.
Correct Answer: A
Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
You are a project manager who uses Project Standard 2013, and your task list includes a flag field that indicates, with Yes or No, if a non-summary task represents a physical deliverable.
Your project involves several tasks marked as deliverables, and management requires you to track how many deliverables are completed. The deliverable is considered completed when the Percent complete field is 100%.
You need to create a formula to calculate the total number of deliverables that are completed.
Which two steps should you perform? (Each correct answer presents part of the solution.
Choose two.)
Your project involves several tasks marked as deliverables, and management requires you to track how many deliverables are completed. The deliverable is considered completed when the Percent complete field is 100%.
You need to create a formula to calculate the total number of deliverables that are completed.
Which two steps should you perform? (Each correct answer presents part of the solution.
Choose two.)
Correct Answer: A,C
Vote an answer
You are a project manager who uses Project Professional 2013.
You manage a project, which involves three other colleagues who also have experience in Project Professional 2013. You and your colleagues are over budget and cannot spend any more money in this project.
You download a specific free app from the Microsoft Office Store.
You need your colleagues to use the same app.
What should you do?
You manage a project, which involves three other colleagues who also have experience in Project Professional 2013. You and your colleagues are over budget and cannot spend any more money in this project.
You download a specific free app from the Microsoft Office Store.
You need your colleagues to use the same app.
What should you do?
Correct Answer: C
Vote an answer
You are an independent project manager who uses Project Professional 2013.
You work in multiple projects for different customers and use one project to manage all their tasks. You create a custom field called Customer Name to identify the customer, and you use the Cost field to monitor the amount of money for each task.
You need to view the most expensive detail tasks in the top of your table without subtotals and summaries.
You turned off summary tasks. What should you do next?
You work in multiple projects for different customers and use one project to manage all their tasks. You create a custom field called Customer Name to identify the customer, and you use the Cost field to monitor the amount of money for each task.
You need to view the most expensive detail tasks in the top of your table without subtotals and summaries.
You turned off summary tasks. What should you do next?
Correct Answer: C
Vote an answer
You create a new schedule by using Microsoft Project. All calendars and working hours use default settings. You configure the schedule to show all assignment units as decimal values.
A resource reports a reduction in availability for your project by two hours per day.
You need to update the project to reflect the availability of the resource.
What are two possible ways to achieve the goal? Each correct answer presents a complete solution.
A resource reports a reduction in availability for your project by two hours per day.
You need to update the project to reflect the availability of the resource.
What are two possible ways to achieve the goal? Each correct answer presents a complete solution.
Correct Answer: B,D
Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
You are a project manager for an organization that uses Project Professional 2013.
You are planning a project schedule that starts on March 1 and lasts four months.
However, the sponsor now asks that the project be delayed to have a finish date of December 31.
You are planning a project schedule that starts on March 1 and lasts four months.
However, the sponsor now asks that the project be delayed to have a finish date of December 31.
Correct Answer: A,C,E
Vote an answer
You update a schedule that you are managing by using Microsoft Project.
After the update, you observe that many of the resources in the schedule are overallocated.
You need to resource level the schedule without changing the current projected finish data for the project.
Which three actions will achieve the goal? Each correct answer presents part of the solution.
After the update, you observe that many of the resources in the schedule are overallocated.
You need to resource level the schedule without changing the current projected finish data for the project.
Which three actions will achieve the goal? Each correct answer presents part of the solution.
Correct Answer: C,D,E
Vote an answer
Your company uses Microsoft Project, and you are setting up an initial planning schedule.
You need to make sure that all new task durations are shown as estimated.
What should you do?
You need to make sure that all new task durations are shown as estimated.
What should you do?
Correct Answer: D