Oracle Planning and Collaboration Cloud 2019 Implementation Essentials - 1Z1-1066 FREE EXAM DUMPS QUESTIONS & ANSWERS
You have executed Planning Data Collection and want to confirm that data has successfully been collected.
Identify the three data combinations that can be viewed using the Maintain Supply Network Model Page.
(Choose three.)
Identify the three data combinations that can be viewed using the Maintain Supply Network Model Page.
(Choose three.)
Correct Answer: A,B,D
Vote an answer
You analyzed your customer's shipment history data at item and organization level. You found that the customer has many new products with limited history.
Does Planning Central support forecasting products with limited history, and what is this process called?
Does Planning Central support forecasting products with limited history, and what is this process called?
Correct Answer: E
Vote an answer
As the planner, you have made some changes to a few of the specifications for items in your simulation sets.
You would like to run one of your existing Demand and Supply Plans that contains this simulation set to see how these changes impact the plan.
Which option shows the steps you must complete in order to ensure that when you run your existing Demand and Supply plan, it contains your changes to the simulation set?
You would like to run one of your existing Demand and Supply Plans that contains this simulation set to see how these changes impact the plan.
Which option shows the steps you must complete in order to ensure that when you run your existing Demand and Supply plan, it contains your changes to the simulation set?
Correct Answer: B
Vote an answer
You want to be able to filter your data by the planner code attribute on the item. Where can you go to do this?
Correct Answer: E
Vote an answer
Your client has made a change to item costs. What type of collection do they need to run to only pick up this change?
Correct Answer: E
Vote an answer
During implementation, the customer would like to use safety stock planning parameters. However, they would like to uncheck "Safety stock change interval to all items." What will the results be if they choose to uncheck this parameter?
Correct Answer: B
Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
You have created several infotiles based on the client requirements. You now want to group them together for display. How do you accomplish this?
Correct Answer: B
Vote an answer
Your client manufactures consumer electronics and has all facilities live on Oracle Cloud. Their latest product has a very complicated manufacturing process and therefore can only be made at one facility (Organization ABC). However, it is ordered all over the world.
How should the Sourcing Rule be set up to accomplish this?
How should the Sourcing Rule be set up to accomplish this?
Correct Answer: A
Vote an answer