Examine the Data Guard configuration after an accidental switchover to Sheep:
DGMGRL> show configuration;
Configuration - Animals
Protection Mode: MaxAvailability
Databases:
sheep - Primary database
dogs - Logical standby database
cats - Physical standby database (disabled)
ORA-16795: the standby database needs to be re-created
Fast-Start Failover: DISABLED
Configuration Status:
SUCCESS
Which three statements will be true after a switchover to Dogs?
Correct Answer: A,B,E Vote an answer
Which THREE statements are TRUE about Global Sequences when connected to a physical standby database with Real-Time Query enabled?
Correct Answer: A,C,D Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
Which three are prerequisites for using Data Guard Broker?
Correct Answer: A,B,E Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
A customer asks for your recommendation regarding this requirement:
1. We plan to have a Data Guard Configuration with one primary database and one physical standby database.
2. We want zero data loss in case of a disaster involving the loss of one component.
3. We want to do Real Application Testing occasionally on the Standby Database.
Which solution, if any, satisfies these requirements?
Correct Answer: B Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
Which four requirements can be met by deploying a logical standby database?
Correct Answer: B,D,E,F Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
Which three are true concerning database states after a successful switchover?
Correct Answer: B,D,E Vote an answer