Your customer has the following setups on the project plan type that they are using for their projects:
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, you perform the following actions:
1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of
01-Jul-2016.
2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions? (Choose the best answer.)
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, you perform the following actions:
1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of
01-Jul-2016.
2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions? (Choose the best answer.)
Correct Answer: C
Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
Which two statements are true about the borrowed and lent cross charge method? (Choose two.)
Correct Answer: A,D
Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes In HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers.
Whichthreeare parameters that are based on which the system identifies the new resources?
Whichthreeare parameters that are based on which the system identifies the new resources?
Correct Answer: A,B,D
Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
Your customer complains that their project resources do not report their time promptly, which has resulted in incorrect reporting of project performance. What should you do to fix this problem? (Choose the best answer.)
Correct Answer: C
Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
Your organization wants to capture the project details for work order labor and equipment resource transactions as part of a project-driven supply chain solution.
Which expenditure type class is recommended for the expenditure types that need to be defined for these type of transactions?
Which expenditure type class is recommended for the expenditure types that need to be defined for these type of transactions?
Correct Answer: C
Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
Whichthreeare part of using the Rapid Implementation for Project Financial Management Applications macro-enabled Microsoft Excel spreadsheet to enter setup data?
Correct Answer: A,C,D
Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).