A supply chain manager mentioned that the required materials for your portfolio might be out of stock next month due to coronavirus. What should you do next?
Correct Answer: B Vote an answer
As a result of optimization, one of the components was deemed necessary to be terminated. One of the executive managers found about this and called you telling you that you should leave this component as it is of interest to her and she wants to see it finalized and that she will make resources available to it if needed. What should be your best course of action?
Correct Answer: B Vote an answer
The portfolio manager defines the portfolio based on a listing of already existing work in the organization and selects the right components in order to be able to prioritize them. What do you use for defining the portfolio based on the listing of work?
Correct Answer: D Vote an answer
A new regulatory mandate has been imposed by the government which highly affected your portfolio. Multiple regulatory components are requested to be added to the portfolio in order to comply with new governmental bank regulations. Initiating these components requires permission from
Correct Answer: B Vote an answer
Your company has acquired another company to expand its product line. Which document should you update to reflect the change in organizational structure?
Correct Answer: A Vote an answer
Assume it was your suggestion to the executive team as the newly appointed Chief Financial Officer for your organization to implement portfolio management. While someone has been identified to be the portfolio manager, you are developing the charter and the structure. In doing so, guidance is provided by the:
Correct Answer: B Vote an answer
Assume as the portfolio manager you have conducted a stakeholder analysis, gap analysis, and a readiness analysis as your cereal company is now entering the ice cream market. A team was formed and located off site to determine whether this market was one in which your company could compete, and its recommendation to do so was accepted by the Portfolio Review Board.
Now you need to:
Correct Answer: B Vote an answer
In determining whether a component is ready to begin work, a portfolio manager should review reports related to:
Correct Answer: D Vote an answer
Each time the Portfolio Governance Group meets the goal is to review the existing components and any that are proposed to ensure the portfolio has the best mix to attain strategic objectives.
As the portfolio manager, you find these meetings, if facilitated accordingly, are effective decision- making sessions. However, you tend to have open issues after every meeting. These open issues:
Correct Answer: D Vote an answer
You are the manager of a major portfolio with a variety of stakeholders and stakeholder groups.
you know that managing communication is key to success and you stress on maintaining a high communication level. You want to start developing your Communication Management Plan and are planning to use
Correct Answer: A Vote an answer