When you create a planning layout, whih objects can you use to define the data columns ? 3 Answers
Correct Answer: A,C,D
Vote an answer
Duringposting, from which object does the system first derive the profit center if the profit center is NOT directly assigned to a network activity?
Correct Answer: A
Vote an answer
You want to settle primary cost elements and secondary cost elements to different receivers. What do you use?
Correct Answer: B
Vote an answer
When do you use an assessment instead of a distribution? 2 answers
Correct Answer: A,B
Vote an answer
To which objects do you settle values of the results analysis? There are TWO correct answers for this question
Correct Answer: A,B
Vote an answer
You want to run an assessment cycle in Profitability Analysis to allocate cost centers costs during period-end closing for your organization. Which of the following objects is part of the assessment cycle?
Correct Answer: A
Vote an answer
What does the internal order settlement profile define? There are THREE correct answers for this question
Correct Answer: A,B,E
Vote an answer
What is the highgest reporting level in management accounting?
Correct Answer: C
Vote an answer
What values flow from Sales and Distribution billing to costing-based Profitability Analysis? 2 answers
Correct Answer: A,C
Vote an answer
When is the standard hierarchyof the controlling area created?
Correct Answer: B
Vote an answer
For which of the following situations would you need to implement the transfer pricesolution in SAP S4/HANA ?
Correct Answer: B
Vote an answer
Which statement best describes a cost center standard hierarchy?
Correct Answer: C
Vote an answer