SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management - C_S4PPM_1909 FREE EXAM DUMPS QUESTIONS & ANSWERS
What is the priority field in the project definition of a project management project used for?
Correct Answer: B
Vote an answer
In project management, what data can be copied from a project template during creation of a new project?
NOTE: There are 3 correct answers to this question.
NOTE: There are 3 correct answers to this question.
Correct Answer: A,B,E
Vote an answer
What influences whether an items is displayed in a specific dashboard scope?
NOTE: There are 3 correct answers to this question
NOTE: There are 3 correct answers to this question
Correct Answer: B,D,E
Vote an answer
You want to use a customer-specific status for items.
How do you configure the status in customizing?
How do you configure the status in customizing?
Correct Answer: A
Vote an answer
Resources are not shown in the Resource Overview
What is the reason for this?
NOTE: There are 2correct answers to this question
What is the reason for this?
NOTE: There are 2correct answers to this question
Correct Answer: A,D
Vote an answer
In portfolio management to which of the following does the logical system refer In the definition of the PS project definition object link?
Correct Answer: D
Vote an answer
You want to configure portfolio management to use Financial planning for manual planning on the item level.
Which of the following settings are required?
NOTE: There are 2correct answers to this question.
Which of the following settings are required?
NOTE: There are 2correct answers to this question.
Correct Answer: A,D
Vote an answer
What must you do before you can use multiple currencies in financial planning in portfolio management?
Correct Answer: D
Vote an answer