For which revenue carrying cost objects does the system perform results analysis?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,E
Vote an answer
What do you do to create a primary cost component split?
There are TWO correct answers for this question
Response:
There are TWO correct answers for this question
Response:
Correct Answer: A,D
Vote an answer
What is the difference when you perform repost line items (TA: KB61) compared to manual reposting of costs (KB11n) for a cost center?
There are TWO correct answers for this question
Response:
There are TWO correct answers for this question
Response:
Correct Answer: A,B
Vote an answer
Which object do you have to assign the cost component structure to?
Response:
Response:
Correct Answer: B
Vote an answer
During posting, from which object does the system first derive the profit center if the profit center is NOT directly assigned to a network activity?
Response:
Response:
Correct Answer: A
Vote an answer
You use a ledger, an additional standard ledger and an extension ledger. You post a general journal entry without indicating a ledger group.
For which ledger(s) are separate line items posted in the universal journal?
Response:
For which ledger(s) are separate line items posted in the universal journal?
Response:
Correct Answer: C
Vote an answer
Which views can you use to analyze the costing results within the costing run tool?
There are THREE correct answers for this question
Response:
There are THREE correct answers for this question
Response:
Correct Answer: A,C,D
Vote an answer
Which main elements do you configure for the overhead costing sheet?
There are TWO correct answers for this question
Response:
There are TWO correct answers for this question
Response:
Correct Answer: B,D
Vote an answer
When you define assessment cycles for the period-end closing in overhead cost accounting, which object can you assign to the cycle segment?
Response:
Response:
Correct Answer: A