The user you advise requests that you make it possible for the user to produce materials for stock, for customer orders, projects, orders and cost centers with production orders.
Where can you make settings to ensure these options?
Correct Answer: C Vote an answer
Which of the following activities within the KANBAN procedure normally triggers subsequent stock posting of the goods receipt?
Correct Answer: A Vote an answer
Which of the following prerequisites have to be fulfilled for production orders to be transferred to a business data entry system via the Plant data collection (PP-PDC) interface? (Choose three.)
Correct Answer: B,D,E Vote an answer
The company that you advise does not want to manage certain value-intensive materials in the warehouse stock. Instead, the user wishes to control material provision in such a way that these materials are procured directly for the production and/or process order.
How can you fulfill this request? (Choose two.)
Correct Answer: A,E Vote an answer
Where are the standard operation times for an operation defined?
Correct Answer: A Vote an answer
Which types of objects can be changed with Engineering Change Management?
(Choose three.)
Correct Answer: B,C,E Vote an answer
An enterprise based in the USA produces an end product that is used with the unit of measure "pound" (LB). The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit kilogram (KG).
Which of the following solutions does SAP ECC offer?
Correct Answer: A Vote an answer
Which functions lead to a reduction in the capacity requirement for an individual operation at a work center? (Choose three.)
Correct Answer: A,B,E Vote an answer