SAP Certified Application Associate - Planning and GATP in SAP SCM APO 7.0 EHP1 - C_TSCM44_65 FREE EXAM DUMPS QUESTIONS & ANSWERS
What influence does the checking horizon have for demands which cannot be confirmed in time?
Correct Answer: B
Vote an answer
The implementation project requires finite scheduling that considers different finiteness levels.
What controls the finiteness level?
Note: There are 2 correct answers to this question.
What controls the finiteness level?
Note: There are 2 correct answers to this question.
Correct Answer: A,B
Vote an answer
The customer wants to use SNP capacity leveling.
Which leveling scenario is supported?
Which leveling scenario is supported?
Correct Answer: B
Vote an answer
Which statements describe macro capabilities for DP and SNP correctly?
Note: There are 3 correct answers to this question.
Note: There are 3 correct answers to this question.
Correct Answer: A,D,E
Vote an answer
Which of the PP/DS options can you configure in Model and Version Management?
Note: There are 3 correct answers to this question.
Note: There are 3 correct answers to this question.
Correct Answer: A,C,E
Vote an answer
What is the relationship between availability check in the MRP 3 view, the checking group and the check mode?
Note: There are 2 correct answers to this question.
Note: There are 2 correct answers to this question.
Correct Answer: C,D
Vote an answer
Which options allow you to monitor resource alerts (capacity overload) ?
Note: There are 2 correct answers to this question.
Note: There are 2 correct answers to this question.
Correct Answer: A,C
Vote an answer
An employee uses the detailed scheduling planning board in APO-PP/DS. Although a particular resource is visible on the board, the employee is unable to plan any operations on it.
What is the reason for this?
What is the reason for this?
Correct Answer: D
Vote an answer