Exam CCMP Topic 4 Question 55 Discussion
Actual exam question for ACMP Global's CCMP exam
Question #: 55
Topic #: 4
Question #: 55
Topic #: 4
Completing the change management effort should include which of the following actions to evaluate the outcomes of the change initiative against the change objectives?
Suggested Answer: D Vote an answer
ACMP requires aformal evaluation of outcomes against objectivesas part of closure. This ensures accountability, provides evidence of success, and informs future projects. Reviewing the change lead (A), employee competencies (B), or sponsor effectiveness (C) may contribute to lessons learned but do not represent the core closure evaluation. The correct evaluation step is option D.
(Reference: ACMP Standard, Process Group 5 - Close; Activity: Evaluate outcomes compared to initial objectives.)
(Reference: ACMP Standard, Process Group 5 - Close; Activity: Evaluate outcomes compared to initial objectives.)
by Ursula at Apr 15, 2026, 02:11 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).