PESTLE is a technique that can be used to determine factors that may impact or influence a project's business case. What does the letter "S" in PESTLE represent?
Suggested Answer: C Vote an answer
Detailed Explanation:
* Sociological Factors:Include societal norms, demographics, and cultural aspects that influence project success.
* PESTLE Context:Addresses Political, Economic, Sociological, Technological, Legal, and Environmental factors.
* Sociological Factors:Include societal norms, demographics, and cultural aspects that influence project success.
* PESTLE Context:Addresses Political, Economic, Sociological, Technological, Legal, and Environmental factors.
by Sandra at May 21, 2026, 12:26 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).