Exam APM-PMQ Topic 1 Question 21 Discussion

Actual exam question for APM's APM-PMQ exam
Question #: 21
Topic #: 1
PESTLE is a technique that can be used to determine factors that may impact or influence a project's business case. What does the letter "S" in PESTLE represent?

Suggested Answer: C Vote an answer

Detailed Explanation:
* Sociological Factors:Include societal norms, demographics, and cultural aspects that influence project success.
* PESTLE Context:Addresses Political, Economic, Sociological, Technological, Legal, and Environmental factors.

by Sandra at May 21, 2026, 12:26 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10