Which of the following are not typical responses to risks?
* Complete root cause analysis to understand why the situation has occurred.
* Reduce the probability of the threat occurring or the impact on the project.
* Change objectives or practices to change the cause of the threat so it can no longer occur.
* There are no acceptable or viable approaches to take to avoid or reduce, so the threat and any residual risk must be managed.
* Prepare a risk management plan to document the risk and give it to your sponsor.
* Pass the responsibility for bearing the impact of the threat from one party to another.
* Complete root cause analysis to understand why the situation has occurred.
* Reduce the probability of the threat occurring or the impact on the project.
* Change objectives or practices to change the cause of the threat so it can no longer occur.
* There are no acceptable or viable approaches to take to avoid or reduce, so the threat and any residual risk must be managed.
* Prepare a risk management plan to document the risk and give it to your sponsor.
* Pass the responsibility for bearing the impact of the threat from one party to another.
Suggested Answer: B Vote an answer
Detailed Explanation:
* Preparing a risk management plan (5) is part of risk planning, not a direct response to risks.
* Preparing a risk management plan (5) is part of risk planning, not a direct response to risks.
by Moses at Dec 16, 2025, 09:27 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).