Exam AgilePM-Practitioner Topic 1 Question 7 Discussion

Actual exam question for APMG-International's AgilePM-Practitioner exam
Question #: 7
Topic #: 1
There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as it evolves.
Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1
1) In order to get an objective
view, the financial transaction
function is to be tested by
someone from Finance who
has had no involvement in its
development.
2) Before the developer works on
the printing function for the
policy documents, the Sales
Manager will review a prototype
of the online application form
for the new coffee shop
insurance product with the
solution tester.
3) Security test scripts have been
provided by the company ' s
bank. These scripts will be used
to test the link from the
company ' s website to the
banking system, which is to be
developed specifically to achieve these tests
4.
The addition of the new coffee
shop insurance product may
threaten the stability of the
existing website. As a primary
route to market this is
unacceptable. The website ' s
capacity to run additional pages
is to be verified before any
other tests are performed.
5.
The Must Have and Should
Have requirements are to be
tested before the Could Have
requirements.
Column 2
* Collaborative Testing
* Repeatable Testing
* Independent Testing
* Prioritised Testing
* Test-Driven Development

Suggested Answer:


Explanation:
* C. Independent Testing
* A. Collaborative Testing
* B. Repeatable Testing
* D. Prioritised Testing
* D. Prioritised Testing
Short Comprehensive Explanation :
* Independent Testing is appropriate when someone from a different department (Finance) with no involvement in the development process conducts the testing to ensure an objective view.
* Collaborative Testing involves various stakeholders, in this case, the Sales Manager and the solution tester, working together to review and test a prototype, promoting early feedback and shared understanding.
* Repeatable Testing is used for security testing where predefined test scripts (provided by the bank) are applied to ensure the system meets specific security standards and can be repeated as needed.
* Prioritised Testing is essential when the project ' s stability and core functionality, such as the website ' s capacity to handle new features, must be confirmed before other tests are conducted to ensure the most critical aspects are addressed first.
* Again, Prioritised Testing is used to ensure that the essential requirements (Must Haves and Should Haves) are tested and validated before moving on to less critical ones (Could Haves), aligning with prioritization in Agile methodologies.
The Agile Project Management (AgilePM) framework and principles, as detailed in the AgilePM Practitioner documents and learning resources, guide the application of these testing concepts within an Agile project environment. These resources emphasize the importance of iterative development, stakeholder collaboration, and prioritization of work to ensure project success and alignment with business needs. Specific references to testing approaches and their application within Agile projects can be found in the official AgilePM handbook and practitioner-level training materials available through APMG International and affiliated training providers.

by Avery at Jul 20, 2026, 04:18 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10