Exam Change-Management-Foundation Topic 2 Question 4 Discussion

Actual exam question for APMG-International's Change-Management-Foundation exam
Question #: 4
Topic #: 2
Which is an engagement level of Mayfield's stakeholder radar technique?

Suggested Answer: B Vote an answer

Explanation
Mayfield's stakeholder radar technique identifies four levels of engagement for stakeholders: required, desired, actual, and planned. The required level of engagement is the minimum level that is necessary for the stakeholder to support the change or at least not resist it. References:
https://apmg-international.com/sites/default/files/Change%20Management%20Foundation%20Sample%20Paper (page 11)

by giu.nicoletti5 at Jan 13, 2024, 01:11 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
giu.nicoletti5
2024-01-13 01:11:20
Selected Answer: D
IS d
upvoted 1 times
...
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10