Which of the following is a purpose of creating a change management plan when preparing for change?
Suggested Answer: D Vote an answer
Explanation
One of the purposes of creating a change management plan when preparing for change is to record a list of all the change risks and the responsive actions required. This helps to identify potential threats and opportunities for the change and plan how to mitigate or exploit them. The other options are not purposes of a change management plan, but rather outcomes or inputs of other processes or activities. References:
https://apmg-international.com/sites/default/files/Change%20Management%20Foundation%20Sample%20Paper (page 11)
One of the purposes of creating a change management plan when preparing for change is to record a list of all the change risks and the responsive actions required. This helps to identify potential threats and opportunities for the change and plan how to mitigate or exploit them. The other options are not purposes of a change management plan, but rather outcomes or inputs of other processes or activities. References:
https://apmg-international.com/sites/default/files/Change%20Management%20Foundation%20Sample%20Paper (page 11)
by Blair at Oct 13, 2025, 01:59 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).