Exam L4M2 Topic 3 Question 64 Discussion

Actual exam question for CIPS's L4M2 exam
Question #: 64
Topic #: 3
Aldar Properties is a property developer in UAE. In last month, it spent $2,160 for 10 tons of steel. In this month, it had planned 10% increment in budget for steel comparing to last month. But the number of orders boosted and total spend on steel reached $1,992.1 while Aldar has imported 11 tons. What is the main cost driver of steel budget?

Suggested Answer: D Vote an answer

In this question, you have to calculate price variance and quantity variance.
Last month, 1 tonne of steel costed $216. This month, the price decreases to $181.1. Price variance = (P1 - P2)*Q2 = ($216-$181.1)*11 = $383.9 Quantity variance = (Q1-Q2)*P1 = -$216 Price variance is greater than quantity variance, therefore, price variance is the main cost driver.
LO 1, AC 1.4

by Hobart at May 02, 2025, 03:47 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10