Under which of the following scenarios an RFQ is most likely to be used?
Suggested Answer: A Vote an answer
The request for quotations is a procurement method that is used for small value procurements of readily available off-the-shelf goods, small value construction works, or small value services procurements. Request for quotations works best under a framework agreement This procurement method is also known as invitation to quote and shopping, and it does not require the preparation of tender documents to the same extent as open tendering, request for proposals or two-stage tendering.
Among 4 options:
- "Purchase of a small number of standardised products under a framework agreement": the products are standardised and there is a framework agreement in place, so RFQ is the best solution.
- "Purchase of complex machinery": Complex machinery is often a large purchase. Furthermore, suppliers' quality may vary. So RFQ is not suitable, instead, depending on the situation, buyer may opt ITT or RFP to purchase this type of machinery.
- "Design of a unique and complex software code": Unique and complex software is not off-the-shelf, thus RFQ is not suitable.
- "When the buying organisation does not know the requirements in details and needs the input from suppliers": When the detailed requirements are unknown, the best solution is request for proposal or developing dialogue with suppliers.
Reference:
- Request for Quotations
- CIPS study guide page 3-4
LO 1, AC 1.1
Among 4 options:
- "Purchase of a small number of standardised products under a framework agreement": the products are standardised and there is a framework agreement in place, so RFQ is the best solution.
- "Purchase of complex machinery": Complex machinery is often a large purchase. Furthermore, suppliers' quality may vary. So RFQ is not suitable, instead, depending on the situation, buyer may opt ITT or RFP to purchase this type of machinery.
- "Design of a unique and complex software code": Unique and complex software is not off-the-shelf, thus RFQ is not suitable.
- "When the buying organisation does not know the requirements in details and needs the input from suppliers": When the detailed requirements are unknown, the best solution is request for proposal or developing dialogue with suppliers.
Reference:
- Request for Quotations
- CIPS study guide page 3-4
LO 1, AC 1.1
by Wade at May 01, 2026, 12:13 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).