Which of the following would be useful tools to incentivise supplier innovation over the duration of the contract?
1. Gainshare arrangement
2. Liquidated damages
3. Service credits
4. Fixed bonus payments
1. Gainshare arrangement
2. Liquidated damages
3. Service credits
4. Fixed bonus payments
Suggested Answer: C Vote an answer
Gainshare is an incentive for cost control
Liquidated damage is common type of disincentive for late completion
Service credit is a remedy for not achieving targets set out in an SLA
Fixed bonus payment is an incentive for early completion
Reference:
LO 3, AC 3.3
Liquidated damage is common type of disincentive for late completion
Service credit is a remedy for not achieving targets set out in an SLA
Fixed bonus payment is an incentive for early completion
Reference:
LO 3, AC 3.3
by Duke at Apr 21, 2025, 11:21 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).