Exam L4M3 Topic 7 Question 118 Discussion

Actual exam question for CIPS's L4M3 exam
Question #: 118
Topic #: 7
A large company supplies a lot of products. Their shipments are often delayed and customers are not satisfied. Which of the following KPIs is most likely to be applied to this situation?

Suggested Answer: B Vote an answer

If the deliveries often delay, buyer should use KPI to measure how many missed deliveries there are and the percentage of total missed deliveries on total number of deliveries for period. OTIF (one-time in-full) delivery might help.
Consignment stock availability means that the supplier holds adequate range/number of units of stock to offer a reliable service Delay damages are the consequences caused by delay of deliveries Technical support is the acceptable quality of technical information/support provided by supplier for goods supplied.
LO 2, AC 2.2

by Joseph at Apr 11, 2025, 02:47 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10