A procurement manager who works in the public sector has received 8 submissions to a tender op-port unity that was advertised on OJEU. The average price submission for the contract was £1m but one supplier has submitted a price of £200,000, which the procurement manager has identified as being 'an abnormally low tender'. What should be the procurement manager's course of action?
Suggested Answer: C Vote an answer
You should investigate automatically low tenders by clarifying the bid with the supplier. It could be they have misunderstood the requirement. Or the bid could be genuine and they can really provide best value for money.
But without enquiring, you just don't know.
But without enquiring, you just don't know.
by Hayden at Nov 16, 2025, 08:21 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).