Exam L4M4 Topic 3 Question 23 Discussion
Actual exam question for CIPS's L4M4 exam
Question #: 23
Topic #: 3
Question #: 23
Topic #: 3
What is a risk of pre-warning a supplier that you will conduct an audit of their facilities?
Suggested Answer: D Vote an answer
A risk of pre-planning an audit is the supplier has time to prepare for it. It's a good thing in that they can get their paperwork in order but the downside is they can overprepare so you don't get a realis-tic representation of what they're doing. One way they can do this is coaching staff in what to say to the auditors.
by Reg at Jan 25, 2025, 04:31 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).