Exam L4M5 Topic 12 Question 40 Discussion

Actual exam question for CIPS's L4M5 exam
Question #: 40
Topic #: 12
During a negotiation, the supplier requests for payment term shortened to 45days from 60 days. Seeing that this proposal lies within the concession plan, the procurement manager asks for 5% discount in return. Is that right thing to do?

Suggested Answer: D Vote an answer

Explanation
When preparing for a negotiation, negotiator should establish a list of tradeables and a concession plan. Good negotiators never give anything away that has not already been planned as part of the bargaining mix in the concession planning stage.
In the above scenario, the procurement manager has planned his own concession, so he can trade with supplier. The answer should be "Yes, since procurement manager has his own cost savings target to achieve and he should make use of supplier's financial status" Table Description automatically generated

LO 2, AC 2.3

by Annabelle at Nov 08, 2025, 11:54 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10