Exam 400-007 Topic 7 Question 147 Discussion
Actual exam question for Cisco's 400-007 exam
Question #: 147
Topic #: 7
Question #: 147
Topic #: 7
Refer to the exhibit.

ACME Mining has four data centers in Santiago. Cape Town. Mumbai, and Beijing, full-mesh connected via a 400 Mb/s EVP-LAN They want to deploy a new mission-critical application with these requirements:
cluster heartbeat 2 Mb/s continuous (250 KB/s)
cluster heartbeat one-way maximum latency 100 ms
These are the current ping tests results between the four data centers:

Which hosting data center pair can host the new application?

ACME Mining has four data centers in Santiago. Cape Town. Mumbai, and Beijing, full-mesh connected via a 400 Mb/s EVP-LAN They want to deploy a new mission-critical application with these requirements:
cluster heartbeat 2 Mb/s continuous (250 KB/s)
cluster heartbeat one-way maximum latency 100 ms
These are the current ping tests results between the four data centers:

Which hosting data center pair can host the new application?
Suggested Answer: F Vote an answer
by Coral at Jan 28, 2024, 04:50 PM