The project manager must create a project charter. Which of the following should be included in the charter?

Suggested Answer: D Vote an answer

The project charter is a high-level authorization document that outlines the purpose, objectives, and identifies key stakeholders. It does not contain detailed schedules, risk management plans, or resource allocation - those come later in the planning process.
Reference: CompTIA Project+ PK0-005 - Project Initiation & Charter Development; CompTIA Cloud+ CV0-
004 Governance & Compliance domain.

by Hale at Nov 18, 2026, 07:53 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10