Exam SK0-005 Topic 4 Question 375 Discussion
Actual exam question for CompTIA's SK0-005 exam
Question #: 375
Topic #: 4
Question #: 375
Topic #: 4
A company has a data center that is located at its headquarters, and it has a warm site that is located 20mi (32km) away, which serves as a DR location. Which of the following should the company design and implement to ensure its DR site is adequate?
Suggested Answer: D Vote an answer
A DR site is a backup site that can be used to restore business operations in case of a disaster that affects the primary site. A warm site is a DR site that has some equipment and data ready to be activated quickly, but not as fast as a hot site that has fully operational systems and data. A cold site is a DR site that has only basic infrastructure and no equipment or data. The location of a DR site is an important factor to consider when designing and implementing a DR plan. A DR site that is too close to the primary site may be affected by the same disaster, such as a power outage, a flood, or an earthquake. A DR site that is too far away from the primary site may incur higher costs and latency issues. Therefore, a good practice is to set up a DR site that is geographically located in another region that has different risk factors and environmental conditions than the primary site. This can help ensure that the DR site is available and accessible when needed. References:
https://www.comptia.org/training/resources/exam-objectives/comptia-server-sk0-005-exam-objectives (Objective 3.3)
https://www.comptia.org/training/resources/exam-objectives/comptia-server-sk0-005-exam-objectives (Objective 3.3)
by Eunice at Apr 22, 2025, 12:03 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).