Exam CMMC-CCA Topic 1 Question 30 Discussion

Actual exam question for Cyber AB's CMMC-CCA exam
Question #: 30
Topic #: 1
An OSC has contacted your C3PAO organization for a prospective CMMC Level 2 assessment. You have been selected to lead the Assessment Team. When ascertaining the assessment conditions and requirements, you discuss the prospective CMMC assessment scope with the OSC. Before proceeding to Phase 2 of the CMMC assessment process, the OSC must complete the following steps of its high-level scoping process, EXCEPT?

Suggested Answer: D Vote an answer

Comprehensive and Detailed Explanation:
The CMMC Assessment Process (CAP) outlines the OSC's scoping steps in Phase 1: identifying assets (Option A), establishing the scope (Option C), and proposing it for validation (Option B). "Evaluate Model Non-Duplication" (Option D) is not a defined step in the CAP or scoping guide, making it the exception. D is correct.
Reference:
CMMC Assessment Process (CAP) v1.0, Section 2.1 (Phase 1: Scoping), p. 8: "OSC steps include asset identification and scope proposal."

by Marcus at Feb 09, 2026, 05:30 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10