During the planning and preparation discussions, a key member of the C3PAO Assessment Team falls ill and is unavailable for the originally scheduled assessment dates. The OSC is eager to proceed as planned and has expressed willingness to accommodate a smaller assessment team. Can the Lead Assessor proceed with the assessment using a reduced assessment team size?
Suggested Answer: A Vote an answer
Comprehensive and Detailed in Depth Explanation:
The CAP allows flexibility in team size if the remaining members are qualified to cover all practices (Option A). Options B, C, and D impose unnecessary restrictions not supported by CAP.
Extract from Official Document (CAP v1.0):
* Section 1.5 - Assessment Team Roles (pg. 16):"The Lead Assessor may proceed with a reduced team if remaining members are qualified to cover all required CMMC practices." References:
CMMC Assessment Process (CAP) v1.0, Section 1.5.
The CAP allows flexibility in team size if the remaining members are qualified to cover all practices (Option A). Options B, C, and D impose unnecessary restrictions not supported by CAP.
Extract from Official Document (CAP v1.0):
* Section 1.5 - Assessment Team Roles (pg. 16):"The Lead Assessor may proceed with a reduced team if remaining members are qualified to cover all required CMMC practices." References:
CMMC Assessment Process (CAP) v1.0, Section 1.5.
by Ada at Nov 24, 2025, 12:14 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).