Question #: 73
Topic #: 1
Question #: 73
Topic #: 1
To claim efficiency measure Insulation for Cold Storage Envelope, which of the following documents is required as evidence at the preliminary certification stage?
Suggested Answer: B Vote an answer
The preliminary certification stage requires specific documentation to verify the implementation of efficiency measures like Insulation for Cold Storage Envelope. The EDGE Certification Protocol outlines the evidence requirements: "For measures involving insulation, such as Insulation for Cold Storage Envelope, the Client must provide drawings at the preliminary certification stage that specify the U-value of the installed insulation to demonstrate compliance with the measure's requirements. The U-value must be lower than the Base Case to qualify for savings" (EDGE Certification Protocol, Section 3.2: Audit Requirements). Option C, drawings showing the U-value specification of the cold storage envelope, directly aligns with this requirement. Option A (calculations of Coefficient of Performance) is irrelevant, as COP applies to HVAC systems, not insulation:
"COP is used for chillers, not insulation measures" (EDGE User Guide, Section 4.2: Energy Efficiency Measures). Option B (manufacturer's data sheets for the HVAC system) is also unrelated, as the measure focuses on the envelope, not HVAC: "HVAC documentation is not required for insulation measures" (EDGE Certification Protocol, Section 3.2: Audit Requirements). Option D (purchase receipts showing the U-value) is more relevant at the post-construction stage: "Purchase receipts are typically required at the post-construction stage to confirm installation, while drawings suffice for design-stage verification" (EDGE Certification Protocol, Section 3.4: Post-Construction Requirements). Thus, drawings with U-value specifications (Option C) are required at preliminary certification.
Reference:EDGE Certification Protocol, Section 3.2: Audit Requirements, Section 3.4: Post-Construction Requirements; EDGE User Guide Version 2.1, Section 4.2: Energy Efficiency Measures.
"COP is used for chillers, not insulation measures" (EDGE User Guide, Section 4.2: Energy Efficiency Measures). Option B (manufacturer's data sheets for the HVAC system) is also unrelated, as the measure focuses on the envelope, not HVAC: "HVAC documentation is not required for insulation measures" (EDGE Certification Protocol, Section 3.2: Audit Requirements). Option D (purchase receipts showing the U-value) is more relevant at the post-construction stage: "Purchase receipts are typically required at the post-construction stage to confirm installation, while drawings suffice for design-stage verification" (EDGE Certification Protocol, Section 3.4: Post-Construction Requirements). Thus, drawings with U-value specifications (Option C) are required at preliminary certification.
Reference:EDGE Certification Protocol, Section 3.2: Audit Requirements, Section 3.4: Post-Construction Requirements; EDGE User Guide Version 2.1, Section 4.2: Energy Efficiency Measures.
by Hugh at Jun 22, 2026, 01:09 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).