Exam Cloud-Digital-Leader Topic 1 Question 202 Discussion
Actual exam question for Google's Cloud-Digital-Leader exam
Question #: 202
Topic #: 1
Question #: 202
Topic #: 1
Your organization runs many workloads in different Google Cloud projects, each linked to the same billing account. Each project's workload costs can vary from month to month, but the overall combined cost of all projects is relatively stable. Your organization needs to optimize its cost.
What should your organization do?
What should your organization do?
Suggested Answer: C Vote an answer
Turn on committed use discount sharing, and create a commitment for the combined usage Sharing your committed use discounts across all your projects reduces the overhead of managing discounts on a per-project basis, and maximizes your savings by pooling all your discounts across your projects' resource usage. If you have multiple projects that share the same Cloud Billing account, you can enable committed use discount sharing so all of your projects within that Cloud Billing account share all of your committed use discount contracts. Your sustained use discounts are also pooled at the same time. That is, sustained use discounts are calculated using the total resources across these projects, rather than just the resources within a single project.
Text Description automatically generated

Reference link- https://cloud.google.com/compute/docs/instances/signing-up-committed-use- discounts#sharing_committed_use_discounts_across_projects
Text Description automatically generated

Reference link- https://cloud.google.com/compute/docs/instances/signing-up-committed-use- discounts#sharing_committed_use_discounts_across_projects
by Benedict at Mar 03, 2026, 07:27 AM