Exam IAM-Certificate Topic 4 Question 61 Discussion

Actual exam question for IAM's IAM-Certificate exam
Question #: 61
Topic #: 4
What are the main cost elements of a whole-life cost approach?

Suggested Answer: D Vote an answer

Whole-life cost elements include costs incurred from the point of asset creation to its final disposal. This covers:
* Installation
* Operations and Maintenance
* Disposal or decommissioning
Exact Extract from IAM - Asset Management: An Anatomy (v4), Section 4.5.1:
"Key cost elements include initial acquisition, installation, maintenance, operation, and final disposal costs."

by Arabela at Jun 26, 2026, 02:14 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.