When auditing an application change control process, which of the following procedures should be included in the scope of the audit?
1. Ensure system change requests are formally initiated, documented, and approved.
2. Ensure processes are in place to prevent emergency changes from taking place.
3. Ensure changes are adequately tested before being placed into the production environment.
4. Evaluate whether the procedures for program change management are adequate.
1. Ensure system change requests are formally initiated, documented, and approved.
2. Ensure processes are in place to prevent emergency changes from taking place.
3. Ensure changes are adequately tested before being placed into the production environment.
4. Evaluate whether the procedures for program change management are adequate.
Suggested Answer: A Vote an answer
by May at Apr 08, 2026, 08:52 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).