A company has recently incurred significant cost overruns on one of its construction projects. Management suspects that these overruns were caused by the contractor improperly accounting for costs related to contract change orders. Which of the following procedures would be appropriate for testing this suspicion?
I. Verify that the contractor has not charged change orders with costs that have already been billed to the original contract.
II. Determine if the contractor has billed for original contract work that was canceled as a result of change orders.
III. Verify that the change orders were properly approved by management.
I. Verify that the contractor has not charged change orders with costs that have already been billed to the original contract.
II. Determine if the contractor has billed for original contract work that was canceled as a result of change orders.
III. Verify that the change orders were properly approved by management.
Suggested Answer: C Vote an answer
Section: Volume A
by Kirk at Jun 29, 2026, 07:58 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).