Which of the following are likely indicators of ineffective change management?
1) IT management is unable to predict how a change will impact interdependent systems or business processes.
2) There have been significant increases in trouble calls or in support hours logged by programmers.
3) There is a lack of turnover in the systems support and business analyst development groups.
4) Emergency changes that bypass the normal control process frequently are deemed necessary.
1) IT management is unable to predict how a change will impact interdependent systems or business processes.
2) There have been significant increases in trouble calls or in support hours logged by programmers.
3) There is a lack of turnover in the systems support and business analyst development groups.
4) Emergency changes that bypass the normal control process frequently are deemed necessary.
Suggested Answer: A Vote an answer
by Peter at Feb 29, 2024, 10:43 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).